Adapazarı Power Plant - 770MW Natural Gas Combined Cycle

Sakarya / Turkey / 2003

Main Contractor : Bechtel - (USA) , Enka A.Ş. - (Turkey) J.V.

Start Date : 01/2001

End Date : 09/2003

Electrical Scope Of Works

  • MV System
  • LV System
  • DCS System
  • Iso Busduct and Generator Circuit Breakers
  • Black Start Generators
  • Heat Tracing System
  • Cathodic Protection System
  • Steam Tracing System
  • Instrumentation System
  • Lighting System
  • Earthing System
  • Fire Alarm System
  • CCTV and Security System
  • Telephone and Data System

 

Adapazarı Power Plant - 770MW Natural Gas Combined Cycle
Adapazarı Power Plant - 770MW Natural Gas Combined Cycle
Adapazarı Power Plant - 770MW Natural Gas Combined Cycle Adapazarı Power Plant - 770MW Natural Gas Combined Cycle
Adapazarı Power Plant - 770MW Natural Gas Combined Cycle Adapazarı Power Plant - 770MW Natural Gas Combined Cycle
Adapazarı Power Plant - 770MW Natural Gas Combined Cycle Adapazarı Power Plant - 770MW Natural Gas Combined Cycle

 

Adapazarı Power Plant is located 150km east of Istanbul, close to city of Sakarya. Natural gas is supplied by BOTAS, the Turkish state-owned gas company.

The plant is based on 770MW power block featuring two gas turbines, two vertical heat recovery steam generators and one 260MW steam turbine.

Gas turbines by GE, steam turbine by Alstom, HRSG by CMI, cooling system by EGI.

 
  • Installation Works
  • Testing
  • Pre-commissioning 
  • Commissioning Support
  • And Design Engineering for Lighting System, Earthing System, Lightning Protection System, and Fire Alarm System