Sabiha Gökçen International Airport

Istanbul / Turkey / 2010

Main Contractor : Limak A.Ş. - (Turkey)

Start Date : 04/2010

End Date : 12/2010

Electrical Scope Of Works

  • Main Power Distribution
  • Lighting System
  • Small power System
  • UPS System
  • Grounding and Lightning Protection System
  • Fire alarm System
  • Access Control System
  • Water Leak Detection  System
  • Master  Clock  System
  • Structured Cable  Network  System
  • Public  Address System
  • Closed Circuit TV System   (CCTV)
  • Master Antenna TV System   (MATV)
  • Disabled Alarm System
  • Audio Visual System

 

Sabiha Gökçen International Airport
Sabiha Gökçen International Airport
Sabiha Gökçen International Airport Sabiha Gökçen International Airport
Sabiha Gökçen International Airport Sabiha Gökçen International Airport
Sabiha Gökçen International Airport Sabiha Gökçen International Airport

 

The new terminal has 25 Million annual passenger capacity conduct domestic and international flights just in one building.

The features and services of the new terminal of the Istanbul Sabiha Gokcen International Airport and outlying buildings are includes a four storey car park with a capacity of about 4718 vehicles, a four storey hotel with 128 rooms, 112 check-in and 24 online check-in counters a VIP building and apron viewing CIP halls, 5000m2 food court for cafes and restaurants, a duty free shopping area with a ground of 4500m2.

Cargo terminal of the airport has 90.000 tons capacity per year.

Multy aircraft ramp system (MARS), allowing simultaneous service to 8 aircrafts with large or 16 middle sized aircraft.

 
 
  • Design Engineering
  • Installation Works
  • All Material Supply
  • Testing
  • Start-up & Commissioning
  • Training & Handover